On the Baku-Tbilisi-Ceyhan Oil Pipeline, High Resolution Aerial Photography and Orthophoto Map Production, Environmental Impact Assessment Analyzes, Security Risk Analyzes, Pipeline Deformation Risk Analyzes were carried out and delivered in 2010, 2011, 2012, 2013, 2014.
Works completed in the corridor area of the Baku Tbilisi Ceyhan Oil Pipeline, which is 1071 km long and 12 km corridor wide; It was finalized by presenting useful results to the employer in order to identify existing risks and to identify potential risk elements in advance and take precautions.